Kepu Selatan Channel Dredging Targeted to Be Complete in October

The Kepu Selatan Connecting Channel dredging process on Jalan Kepu Selatan, Kemayoran Urban Village, Kemayoran Sub-district, Central Jakarta has reached 90 percent.

It is targeted to be finished in two weeks ahead

"It is targeted to be finished in two weeks ahead," expressed Kemayoran Sub-district Water Resources Executing Unit Head, Yursid Suryanegara, Wednesday (9/18).

This channel is targeted to be dredged up to 329 meters length that has been ongoing since August. Thus far it has reached 269 meters. 

Pluit Reservoir Dredging Has Reached 30 Percent

"We dredge mud and waste that triggers siltation up to 50 centimeters. We normalize the channel up to 120 centimeters depth," he explained.

From the channel, the personnel have transported 135 cubic meters of mud and waste.

"To do it, we have sent seven personnel to the location," he told.

Linked News
Popular News indeks
  1. May Day: Transjakarta Service Adjustments

    access_time01-05-2026 remove_red_eye838 personAldi Geri Lumban Tobing
  2. Dinkes Sets Up Health Posts for May Day Events

    access_time01-05-2026 remove_red_eye587 personDessy Suciati
  3. City Deploys Massive Cleanup Force for May Day at Monas

    access_time01-05-2026 remove_red_eye579 personAldi Geri Lumban Tobing
  4. The Lights-Out Action Successfully Reduces Carbon Emissions

    access_time27-04-2026 remove_red_eye566 personAldi Geri Lumban Tobing
  5. MRT Jakarta Urged to Enhance Power Outage Mitigation System

    access_time27-04-2026 remove_red_eye549 personFakhrizal Fakhri